A lead time is not a single production duration. It is a chain of decisions, approvals, material arrivals and release points. When a buyer asks "how long?", the useful answer is which stage we are talking about.

Illustrative factory production area with a laser cutter and staged cabinet frames
Illustrative image. Lead time depends on drawing approval, material availability, production scheduling and shipment.

1. Drawing review and DFM

This is the first one to two weeks for a new design. We check bend radius, weld access, component fit, service access and finish coverage. Most delays at this stage come from open questions: a dimension that is undefined, a component that has not been selected, or a finish that has no reference sample. Send the questions early, not with the PO.

2. Material procurement

Standard cold-rolled sheet is usually available quickly. Named grades, galvanized sheet, stainless, specified hardware brands and long cables can add one to three weeks. If a component is on your drawing, tell us at the inquiry stage whether you will supply it or whether we should source it.

3. First article approval

A sample or first article must be approved before the batch is released. This can take a few days or a couple of weeks, depending on how quickly the customer can review and sign. The practical advice: nominate one person who can approve, and agree what the approval covers.

4. Production scheduling

Sheet metal, coating and assembly are separate stations. A cabinet that needs a special powder colour or a coating slot may wait for the next batch. Ask about the coating schedule when you place the order, not after.

5. Integration and testing

If the scope includes hardware or software loading, this stage adds time. Every component needs to be present, the BOM needs to be frozen, and the test procedure needs to be agreed. Late component changes here are the most expensive kind.

6. Inspection, packing and documents

Final inspection, carton marking, crate building and document preparation. Export crates take time to build properly. Rushing this stage is how a good cabinet arrives damaged.

7. Booking and transit

Production completion is not arrival. Container availability, cut-off times, customs and the final mile all sit outside the factory gate.

The shortest lead time we can offer starts with a complete inquiry. The longest one usually starts with 'we will send the drawing later'.

8. What shortens the schedule

  • Send a drawing or a reference photo with the first inquiry.
  • Freeze the BOM before production release.
  • Name one approver for the first article.
  • Confirm colour, branding and packing at the same time as the technical scope.
  • Tell us the required delivery date and the destination.

Send us the drawing and the date you need the goods. We will return a stage-by-stage schedule with the open points marked.