A cabinet can leave a factory in good condition and still arrive with a bent door or a chipped corner. Long sea routes, container handling and last-mile unloading are real risks. The receiving check is not about finding fault. It is about separating transport damage from manufacturing error while the evidence is still available.

Row of finished terminal cabinets staged in the ENERAREA factory before packing
Cabinets staged before packing. Every unit should be traceable to a carton mark and a packing list entry.

Before the container is opened

Photograph the container number and seal before breaking the seal. If the seal number does not match the documents, stop and record it. Note visible damage to the container exterior. Check whether desiccant or humidity indicators were placed inside and record their condition. A damp container is a common cause of finish problems that appear weeks later.

1. Match the documents first

Keep the packing list, commercial invoice and carton marks together. Count the cartons before opening any of them. Confirm that the model numbers and quantities on the carton labels match the packing list. This step is quick and it is where most claims are won or lost.

2. Photograph before unpacking

Take an overall photo of the loaded container, then one of each carton before it is opened. If the outer carton is crushed, photograph that carton from several angles before cutting the tape. Once packing is removed, the condition of the outer package can no longer be proven.

3. Check the finish under reasonable light

Inspect in daylight or neutral white light, not in a dim warehouse corner. A powder-coated surface should be uniform, without runs, orange peel beyond the agreed standard, or bare edges. Minor variations between separately coated batches are normal for RAL colours. Record them as a batch note, not as a defect, unless the agreed sample says otherwise.

4. Test doors, locks and hinges

Open and close every door. A door that rubs after installation is often a transport shift, but it can also be a hinge alignment issue from assembly. Check that keys operate smoothly and that every lock is supplied with the agreed number of keys. Cycle each hinge a few times and listen for binding.

5. Verify earthing and interfaces

Where an earthing stud or bonding point was specified, confirm it is present and connected to bare metal. Check that cutouts and mounting brackets match the approved drawing before drilling anything on site. It is far cheaper to resolve a bracket position at receiving than after installation.

6. Record what you find

Keep one shared file per shipment: photos, a short note for each carton, and the inspection date. Send it to the supplier even when everything is fine. A clean receiving record is useful the next time a question comes up about a unit that has been in service for a year.

Photograph first, unpack second. The outer carton is part of the evidence and it disappears within minutes.

If there is damage

Report it promptly, with photos of the carton and the unit together. Keep the packing material until the claim is closed. Separate visible transport damage from a suspected build issue in the first message; it makes the investigation much faster for everyone involved.

We include a packing list and carton marks with every shipment and can provide pre-shipment photos on request. If you would like a receiving template adapted to your project, ask for one with your next inquiry.